Gasworks set to go on for five weeks have been delayed. Farleigh Lane and Glebe Lane in Maidstone were both expected to close yesterday (March 4). The closures are to allow for gas main replacements by SGN. However, this has now been delayed due to other works in the area. A spokesman from SGN said: “The start of our work in Farleigh Lane has been postponed by one week. “This is due to our engineering team finding additional pipes where they’re currently working in nearby Terminus Road. “We’re sorry for the delay to this essential work and thank the local community for their patience and under…